École des Pionniers-de-Maillardville is a LEED Gold certified three-phase seismic replacement project, replacing an existing nearly 60-year-old school for School District 93. Phase 1 was the construction of the new school, Phase 2 was the demolition of the existing school, and Phase 3 was the landscaping, play areas, and parking lot construction in place of the demolished school. During Phase 1 construction, the new K-12 school borders the existing school in an “L” shape. The close proximity of the new construction relative to the existing occupied school provides Yellowridge Construction with logistical challenges and special safety measures to keep aware of.
The new 7,161 m2, two-storey school consists of cast-in-place concrete foundations, columns, walls, and suspended slabs, as well as glulam beams, structural steel, nail-laminated timber (NLT) panels, and conventional wood framing. Exterior finishes consist of metal cladding, brick veneer, SBS roofing, and aluminum windows & doors. Working on a site with an existing occupied building and young kids running around presented challenges that are like other successful projects we’ve completed on occupied sites. Maintaining public safety, minimizing noise disruptions, avoiding weather impacts, etc., while meeting the construction budget and schedule was a key to Yellowridge’s success on this project.
Value
Size
Delivery Method
Date
Location
Client
$26,845,797
7,161 m²
Stipulated Sum
2020
Port Coquitlam, BC
School District No 93 (Conseil scolaire francophone de la C.-B.)